NOTICE OF HEARING
APPLICATION NO. 1451729
TERASEN PIPELINES (CORRIDOR) INC.
SCOTFORD UPGRADER TO TRANS MOUNTAIN PIPELINE TERMINAL

Take Notice that the Alberta Energy and Utilities Board (EUB/Board) will hold a public hearing of Application No. 1451729 at the Best Western Sherwood Hotel and Conference Centre, 2100 Premier Way, Sherwood Park, Alberta, commencing on Tuesday, April 24, 2007 at the hour of 9:00 a.m. All interveners to this proceeding must be present at the commencement of the hearing to register their appearance.

Nature of the Application
Terasen Pipelines (Corridor) Inc. (Terasen) has applied pursuant to Part 4 of the Pipeline Act for approval to construct and operate a pipeline and one associated pipeline installation. The purpose of the pipeline would be to transport crude oil from Terasen’s existing Scotford South Pump Station, located at Legal Subdivision (LSD) 7, Section 31, Township 55, Range 21, West of the 4th Meridian, to the Trans Mountain Pipeline Terminal near Edmonton, located at LSD 3-5-53-23W4M. The proposed pipeline would be approximately 43 kilometres (km) in length, with an outside diameter (OD) of 508 millimetres (mm). The associated pipeline installation would be an addition to Terasen’s existing Scotford South Pump Station located at LSD 7-31-55-21W4M.

Additional Information
To obtain additional information or a copy of the application, contact

Terasen Pipelines (Corridor) Inc.
C/O Kinder Morgan Canada Inc.
Suite 2700, 300 – 5 Avenue SW
Calgary, Alberta T2P 5J2
Attention: Peter Forrester, Senior Legal Counsel
Telephone: (403) 514-6643
Fax: (403) 514-6622

A copy of the application is available for viewing at the following EUB offices:

EUB Information Services
Main Floor, 640 – 5 Avenue SW
Calgary, Alberta T2P 3G4
Telephone: (403) 297-8190

EUB St. Albert Field Centre
Main Floor, 30 Winston Churchill Avenue
St. Albert, Alberta T8N 3A3
Telephone: (780) 460-3800

For information about EUB procedures, contact

Applications Branch, Facilities Applications Group
Attention: Phil Didow
Telephone: (403) 297-8103
Fax: (403) 297-4117
E-mail: phil.didow@gov.ab.ca

To File a Submission
Any person intending to make a submission with respect to the hearing of Application No. 1451729 shall file on or before 4:00 p.m., Tuesday, April 10, 2007. Send one copy of your submission to the applicant at the name and address above and ten copies to

Phil Didow, Applications Coordinator
Applications Branch, Facilities Applications Group
Alberta Energy and Utilities Board
640 – 5 Avenue SW
Calgary, Alberta T2P 3G4

Notes
Any submission filed shall contain the following:

(a) a concise statement indicating
  
     (i) the manner in which the intervener’s rights may be directly and adversely affected by a decision of the Board on the proceeding,

     (ii) the nature and scope of the intervener’s intended participation,

     (iii) the disposition of the proceeding that the intervener advocates, if any,

     (iv) the facts the intervener proposes to show in evidence,

     (v) the reasons why the intervener believes the Board should decide in the manner that the intervener advocates, and

     (vi) the intervener’s efforts, if any, to resolve issues associated with the proceeding directly with the applicant;

(b) the name, address in Alberta, telephone number, fax number and, if available, e-mail address of the intervener;

(c) if the intervener is represented by a representative, the name, address in Alberta, telephone number, fax number and, if available, e-mail address of the representative; and

(d) if the intervener is an unincorporated organization, the nature of the intervener’s membership.

If you have an interest in this matter, you are required to make a submission with respect to this application even if you have previously filed a submission with the Board or with Terasen on this application.

If there are no submissions received, this hearing may be cancelled and the EUB will continue to process the application without further notice or without a hearing.

Submissions relating exclusively to compensation for land usage are not dealt with by the EUB and should be addressed to the Alberta Surface Rights Board.

In accordance with Section 12 of the Alberta Energy and Utilities Board Rules of Practice, all documents filed in respect of this proceeding must be placed on the public record unless otherwise ordered by the Board.

In accordance with Section 23.1 of the Alberta Energy and Utilities Board Rules of Practice, a person who intends to raise a question of constitutional law before the Board must give notice in accordance with Section 12 of the Administrative Procedures and Jurisdiction Act and its regulation.

In accordance with Section 38 of the Alberta Energy and Utilities Board Rules of Practice, witnesses must give evidence under oath or affirmation.


Issued at Calgary, Alberta, on March 12, 2007.

ALBERTA ENERGY AND UTILITIES BOARD
Douglas A. Larder, Q.C., General Counsel