Industry Zone Rules, Regulations, Requirements
|
|
|
 |
|
Printer Friendly Version
Directive 056: Frequently Asked Questions – Pipelines Technical
|
|
SURFACE PIPELINES
|
| Question | Do I require a Directive 056 pipeline licence if I am planning to construct surface pipelines associated with an approved in situ oil sands scheme contained within the area of a single blocked MSL issued by SRD? |
| Answer | The ERCB has fielded numerous queries regarding whether or not Directive 056 licences are required for in situ oil sands surface pipelines if the subject pipelines extend beyond the lease boundary of a well pad, facility, or central processing plant but are wholly contained within a single blocked MSL area.
It appears that a blocked MSL area boundary may be misinterpreted as a single surface lease boundary. Consequently, any surface pipelines wholly contained within a blocked MSL that connect a well pad to a central processing plant might be erroneously considered exempt, as set out in Directive 056, Section 6.5.2.
The ERCB would like to clarify that the facility surface lease boundary described in both Directive 056, Section 6.5.2, and the Pipeline Regulation, Part 1, Section 3(3b), is not the same as the area boundary defining a blocked MSL issued by SRD. Rather, a facility surface lease boundary is specific to the lease boundary of each well pad, facility, or central processing plant.
In situ oil sands surface pipelines wholly contained within the boundary of a well pad, facility, or central processing plant and also located within a blocked MSL would not require a Directive 056 licence.
In situ oil sands surface pipelines that extend beyond the well pad, facility, or central processing plant lease boundary but are still within the blocked MSL area boundary require a Directive 056 pipeline application to be submitted and approved prior to construction. In such instances, the participant involvement requirements conducted under Directive 023: Guidelines Respecting an Application for a Commercial Crude Bitumen Recovery and Upgrading Project would satisfy the participant involvement requirements for the Directive 056 application.
Applicants are strongly encouraged to review existing in situ oil sands surface pipelines to ensure that they meet current Directive 056 licensing requirements. Any applicants that identify existing in situ oil sands surface pipelines that require licensing must submit to the Facilities Applications Audit Section a complete self-disclosure application, as set out in Process Clarification for Licensing Pipeline Amendments, Scenario 3.
Companies are reminded that licences for surface pipelines associated with oil sands mine approvals are not issued under Directive 056 unless the pipelines cross a public road or watercourse.
|
|
PERMANENT BI-DIRECTIONAL FLOW PIPELINE
|
| Question | I am planning to permanently operate a pipeline bi-directionally. How should I submit the request to the ERCB for review? |
| Answer |
Submit an application to ERCB Facilities Applications for any request for permanent bi-directional flow pipeline operations. Temporary bi-directional flow pipeline requests are currently submitted and reviewed by ERCB Pipeline Operations.
The ERCB needs to review and document all pipelines being licensed for permanent bi-directional flow before approval, whether the requests are for new pipelines or for amendments to existing lines. The applicant must file its application as nonroutine by filling out all applicable questions on Schedules 3, 3.1, and 3.2, including the following:
1) Schedule 3: Pipeline Licence Application
Under Step 5: Licence Amendment Only, check “Other” and enter “Perm. Bi-directional.”
2) Schedule 3.1: Segment/Installation Identification
Under Step 4: Pipe Location and Status, enter the “From” location and “To” location according to the project’s most common direction of flow.
3) Schedule 3.2: Technical/Environmental Information
Under Step 2: Technical Considerations, check “No” for Question 3: The pipeline meets all current applicable
CSA Z662
standards.
The following is the minimum supporting information applicants must submit with each application:
- A description of the proposed project and an explanation of the need for a permanent bi-directional flow pipeline.
- Confirmation that the requirements of CSA Z662 and the
Pipeline Act
are met.
- A description of the pipeline design and configuration, its suitability for the difference in pressure gradient to operate in both directions, and the suitability of the corrosion control for the bi-directional flow operation.
- A description of the tie-in compatibility for both flow directions (e.g., maximum operating pressures, substance, etc.).
- A description of the internal and external condition of the pipeline.
- A pipeline piping & instrumentation diagram.
- A pipeline right-of-way plan.
- A pipeline base map.
|
|
E
NVIRONMENTAL REQUIREMENTS
|
|
Question:
| What are the requirements for a proposed pipeline right-of-way (ROW) that will be routed through a water body as defined by the Water Act, and how do I fill out
Directive 056
Schedule 3.2 – Step 6, Question 2? |
|
Answer:
|
If the proposed ROW crosses a water body as defined by the
Water Act
but not by the
Code of Practice for Pipelines and Telecommunication Lines Crossing a Water Body
, the applicant, before licensing, must contact Alberta Environment (AENV) to determine if
Water Act
approval is necessary. The
Code of Practice
defines a water body as having a defined bed and bank, whether or not water is continuously present, but does not include fish-bearing lakes.
If AENV determines that
Water Act
approval is not required, the applicant may proceed with an application submission. If AENV determines that
Water Ac
t approval is required, the applicant may still proceed with an application submission but must get
Water Act
approval prior to construction.
When filling out Schedule 3.2 – Step 6, Question 2:
YES
means that you will notify AENV as required by the
Code of Practice
or, if the
Code of Practice
does not apply, that you have consulted with AENV about the need for
Water Act
approval.
N/A
means that no water body crossing as defined by the
Water Act
is involved.
|
|
Page Last Updated: November 21, 2011 |
|